With the substantial growth of my country's investment in scientific research activities, the number of scientific researchers and scientific research results are increasing rapidly, and laboratory sewage has also become a key object of treatment. Laboratory sewage has its own special properties, such as small amount, strong discontinuity, high hazard, and complex and changeable components. Therefore, professional equipment is required for the treatment of laboratory sewage. Nowadays, most laboratory sewage treatment equipment is used. But many people don't know it very well. Let's introduce its related construction standards.
Relevant construction standards for laboratory sewage treatment plants:
1. In the process of construction, commissioning and acceptance, all parts involving mechanical installation, pipeline construction, welding process, monitoring instruments and program control should be used in conjunction with design regulations, national standards and corresponding technical conditions.
2. The construction shall be carried out according to the design drawings and the relevant technical documents of the manufacturer. Before the equipment is in place, the construction unit should check the following items together with the installation, civil construction, supervision and other units:
1. The geometric size, corresponding position and elevation of the equipment foundation shall meet the design requirements;
2. The size and position of embedded parts and reserved holes on reinforced concrete beams, columns and equipment foundations should meet the design requirements;
3. A cushion should be made on the basis of the flat-bottomed water tank equipment. The center of the cushion should have a slope outward, and the center should be 15mm-20mm higher than the edge.
3. Before the adjustment and trial operation, the civil construction should complete the following work:
1. The anti-corrosion floor, anti-corrosion channel and neutralization tank should be completed and accepted for indoor and outdoor water treatment. The drainage and slag discharge channels are unobstructed, the cover plate of the channel is complete, and the board surface is flush with the ground;
2. The interior painting, painting, ground, platform, stairs and doors and windows of the water treatment room should be completed according to the design requirements;
3. The laboratory facilities such as water supply, ventilation, air conditioning, lighting, power supply and test bench shall be completed according to the design requirements;
4. The structures and anti-corrosion and ventilation facilities of the acid-base storage warehouse should all be completed and accepted.
4. All devices have been installed and can be put into use.
5. The electrical, thermal, chemical instruments and operation panels related to the water treatment system should be installed and calibrated, with correct instructions, sensitive operation, and can be put into use (excluding program-controlled devices).
6. The lighting and communication facilities should be able to meet the normal progress of the trial operation.
7. Rotating machinery should pass the test run of the branch.
8. All pipes and equipment should be painted according to the relevant regulations.
9. The specifications of the required filter materials, exchangers and medicines should meet the design requirements, the quantity should meet the needs of starting the trial operation, and the filling should be completed.
The above are the relevant construction standards for laboratory sewage treatment equipment. As sewage treatment gradually becomes a key component of urban construction, sewage treatment equipment has gradually become the key to contemporary urban flood control, sewage treatment, domestic power supply, and wastewater collection and transportation. equipment, and all walks of life need to pay certain attention to it, so as to better carry out water pollution control。
About us
Company profileHonorary qualificationEnterprise dynamicsTechnical articlesProduct display
Laboratory and medical sewage treatment system Water system of laboratory science and Education Institute Water system for pharmaceutical industryColumn navigation
Product Center Project case Video Center Service supportContact us
Online MessageContact uscopyright © 2022 Nanjing Yipu Yida Technology Development Co., Ltd Al Rights Reseved Record number:苏ICP备19073731号-1 Sitemap.xml Manage login technical support:Chemical Industry Instrument Website